Wilson Renovation

The district completed stage one of its renovation with funds from the 2001 bond. Phase one was completed in August 2006. A therapeutic learning center was added to the school along with a new state-of-the-art library and media center to allow students to explore learning with the help of new technologies. Also, the career center, guidance center and administrative offices were updated and located at the new front of the school.

The Wilson project involved the replacement of 85,765 square feet of instructional space and the addition of 9,500 of new construction.

Wilson High School received a shiny new addition thanks to the 2001 bond.
Architect's renderings of the remodeled new Wilson High School

 

 

New Wilson High School elliptical courtyard
The remodel was phase one in a development plan to change Wilson's campus layout into a more traditional one

.

 

 

 

The project added 42 classrooms in total, including: nine science classrooms, six business and marketing classrooms, and two remodeled and expanded art rooms.
One three-story building replaced five previously existing structures and eight portables on the school grounds.


 